180m³ commercial concrete mixing plant is a large-scale concrete mixing plant. Many commercial mixing enterprises will choose this type of equipment. How to plan the site of 180m³ commercial concrete mixing plant?
1.180m³ the overall planning area of the commercial concrete mixing plant shall not be less than 30 mu. Automatic car washing device shall be set at the main exit of the vehicle to effectively clean the commercial concrete truck, gravel truck, bulk cement truck and other large freight vehicles in time; The production area and living area shall be separated. There shall be enough green belts in the station. The station shall be separated by transparent or green walls, with a height of ≥ 2m, and open construction is not allowed.
2.180m³ in addition to the production area, the commercial concrete mixing plant shall be equipped with laboratory, office building, parking lot, car washing platform, testing platform, culture and entertainment and other relevant facilities.
3.180m³ diversion ditches must be reasonably set around and inside the commercial concrete mixing plant to collect sewage, so as to ensure that the sewage in the plant does not overflow; At least 3 clarification (sedimentation) tanks with a single volume of not less than 40m3 shall be set in the station for classified sedimentation of sewage; No less than 1 clean water tank with a single volume of no less than 60m3 and no less than 3 slurry mixing tanks with a single volume of no less than 20m3 shall be set to treat and utilize the slurry water.
4. If slurry pressure filtration system is adopted, clarification (sedimentation) tank, clean water tank and slurry mixing tank shall be set according to the requirements of supporting equipment.
5. A closed molding sand quarry with an area of no less than 3000 m2 shall be set.
6. According to the design of the main building of 180m³ commercial concrete mixing plant, the special charging area for bulk powder truck shall be reasonably set, and the semi closed design shall be adopted to reduce and isolate the noise during charging.
7.180m³ within the scope of commercial concrete mixing plant, main and secondary lanes shall be reasonably set according to different driving vehicles. The width of main road shall not be less than 10m, the width of secondary road shall not be less than 8m, and the turning radius of mechanical vehicle road shall not be less than 12m; Independent sidewalks shall be set to ensure the diversion of people and vehicles in the office area. The ground of station roads and production operation areas shall be hardened with dust-free cement concrete or asphalt concrete. Measures shall be taken to keep the roads in the station clean and there shall be no visible dust when vehicles are driving.
8. The unhardened open space in the living area and office area shall be afforested, and the greening rate of the station shall not be less than 15%, and the three-dimensional greening of buildings shall be actively promoted.