Fixed concrete mixing plant operation points

2014-07-03

concrete mixing plant
 Fixed concrete mixing plant should be installed on firm a pedestal. when fixed for a long time, should be buried land bolt; when used in the short term, should be laid on stand wood blocking and leveling steadier

1. Fixed mixer control console, should allow the operator to see each working condition. Rubber sheets or electric mixer control board, should be fitted dry wood.
2. Hopper into the lowest position, between the hopper and the ground, should add a layer of cushion wood.
3. The workers should check and correction instructions water of the water supply system and the actual water consistency; When the error is more than 2%, should check the pipeline leaking point, or should correct the throttle valve.
4.The workers should observe the workings of the mechanical, when there are abnormal or bearing the high temperature rise phenomenon, should stop check; When this stationary concrete mixing station  need repair, it should be within the mixing drum of concrete was removed, and then for maintenance.
 